Mechanical design of turbine blades in renewable wind technology
The essence of the group’s engineering scenario encompasses the development of a sustainable wind turbine design that can convert wind into usable energy for the roofs of residential housing. The focus of the design was to work out a wind turbine blade with the purpose of converting wind into energy that is applicable for residential use.

(The deflecting stimulation of turbine in Inventor)
Fri-07_P1_DesignReport (2)-1-30.pdf
Fri-07_P1_DesignReport (2)-1-30.pdf
Fri-07_P1_DesignReport (2)-31-49.pdf
In this Project, I have learned how to use grata to select material and use inventor to create the model of turbine blade. However, I need to improve the oral communication between team member and the technical skills as well
For the responsibility of coordinator, I finished the log book but the organization is little bit messy, This could be improve next time
| Meeting date | Attendees | Topics discussed | Task | Due | Comments | Location |
|---|---|---|---|---|---|---|
| 23-Sep | Ke Emily Zhenghan Makayla | Assigns administrative roles. Form a team chat. Form a preliminary Gantt chart. | Shared task: Milestone0 Preliminary Gantt Chart | 28-Sep | A.B.B C419 | |
| 23-Sep | Ke Emily Zhenghan Makayla | Initialize problem statement. Create Objective tree for different scenarios. | Shared task: Milestone 1 | 28-Sep | A.B.B C419 | |
| 28-Sep | Ke Emily Zhenghan Makayla | Assign a Scenario (roof generator). Initialize problem statement. Finalize object tree for assigned scenario. | Shared task: Milestone2 | 29-Sep | A.B.B C419 | |
| 6-Oct | Ke Emily Makayla | Use primary and Secondary objective to form the MPI. Use MPI as the standard of material choose for roof generator on Granta. Rank the top 5 materials individually, consolidate and narrow them to the final selection. Justify the reason of chosen material. | Shared task: Milestone3A | 6-Oct | Zhenghan absented due to covid-19 | |
| ETB 125 | ||||||
| 7-Oct | Ke Emily Makayla | Build up the solid Model of the wind turbine. Analyze the wind turbine blade deflection simulation. | Shared task: Milestone3B | 7-Oct | Zhenghan absented due to covid-19 | A.B.B C419 |
| 21-Oct | Ke Emily Zhenghan Makayla | Refine turbine blade thickness though deflection simulation. | ||||
| Peer interview and record what have we learnt from them. | Shared task: Milestone4 | 21-Oct | A.B.B C419 | |||
| 26-Oct | Ke Emily Zhenghan Makayla | Write design summary and summarize previous milestone work. Replenish Reference and Appendices | Shared task: Final Deliverable | 2-Nov | PGCLL M21 | |
| 31-Oct | Ke Emily Zhenghan Makayla | Review and check Design Project Report Sign academic integrity statement. Submit the Design Project Report. | Shared task: Final Deliverable | 2-Nov | PGCLL M21 |
| Meeting date | Attendees | Topics discussed | Task | Due | Comments | Location |
|---|---|---|---|---|---|---|
| 23-Sep | Ke Emily Zhenghan Makayla | Assigns administrative roles. Form a team chat. Form a preliminary Gantt chart. | Shared task: Milestone0 Preliminary Gantt Chart | 28-Sep | A.B.B C419 | |
| 23-Sep | Ke Emily Zhenghan Makayla | Initialize problem statement. Create Objective tree for different scenarios. | Shared task: Milestone 1 | 28-Sep | A.B.B C419 | |
| 28-Sep | Ke Emily Zhenghan Makayla | Assign a Scenario (roof generator). Initialize problem statement. Finalize object tree for assigned scenario. | Shared task: Milestone2 | 29-Sep | A.B.B C419 | |
| 6-Oct | Ke Emily Makayla | Use primary and Secondary objective to form the MPI. Use MPI as the standard of material choose for roof generator on Granta. Rank the top 5 materials individually, consolidate and narrow them to the final selection. Justify the reason of chosen material. | Shared task: Milestone3A | 6-Oct | Zhenghan absented due to covid-19 | |
| ETB 125 | ||||||
| 7-Oct | Ke Emily Makayla | Build up the solid Model of the wind turbine. Analyze the wind turbine blade deflection simulation. | Shared task: Milestone3B | 7-Oct | Zhenghan absented due to covid-19 | A.B.B C419 |
| 21-Oct | Ke Emily Zhenghan Makayla | Refine turbine blade thickness though deflection simulation. | ||||
| Peer interview and record what have we learnt from them. | Shared task: Milestone4 | 21-Oct | A.B.B C419 | |||
| 26-Oct | Ke Emily Zhenghan Makayla | Write design summary and summarize previous milestone work. Replenish Reference and Appendices | Shared task: Final Deliverable | 2-Nov | PGCLL M21 | |
| 31-Oct | Ke Emily Zhenghan Makayla | Review and check Design Project Report Sign academic integrity statement. Submit the Design Project Report. | Shared task: Final Deliverable | 2-Nov | PGCLL M21 |